The best construction plan for the concrete in summer(3)
Release date: 2017-12-08
This is the last article in the series articles of《The best concrete construction plan in Summer 》. Xiangtan Huaxing Material Co.,Ltd have introduced the best concrete construction program in this summer. We hope that these articles can play a role in your construction.
The final strength of the concrete poured in the hot weather will be reduced. Its influence factors are as below:
(1) The temperature of the concrete is higher;
(2) Coagulation and early strength growth faster;
(3) Increased water consumption at the same slump requirements.
Action:
(1) Sprinkle water onto the aggregate pile and cool down by evaporation of water;
(2) Adding a retarder to the concrete;
(3) If necessary, with ice instead of part of the mixed water;
(4) Mixed with fly ash to regulate the impact of hot weather;
(5) Increase the amount of cement appropriately in concrete per cubic meter.
That’s all of the series articles of《The best concrete construction plan in Summer 》,we will post more related articles. Hope your continue focus, thanks!The following products is concrete pump spare parts which may need to use in the construction.More detail,pls click the picture.